Difference between revisions of "Drava - Kleblach"

From REFORM wiki
Jump to: navigation, search
(Key features of the case study)
(Site description)
Line 12: Line 12:
  
 
==Site description==
 
==Site description==
 +
 +
The Austrian river Drava (in German “Drau”) is part of the Danube catchment. The source of the river is in the Italian municipality Toblach where it continues its flow 264 km along the border between the Central Alps and the Southern Alps and across the Austrian federal states Tyrol and Carinthia. In Osijek (Croatia), the river joins the Danube River after 707 km in total. The site of the restoration project is located near the village of Klebach in Carinthia. At this point the Drava has a discharge basin of roughly 2500 km². The average annual flow of the river near the site is 63m³/s. The river at the site was historically braided with gravel banks in the channel. Until approximately 140 years ago, the Upper Drava was a free flowing, meandering mountain river with numerous braiding stretches due to alluvial cones of the tributaries. In this dynamic river system with its annual floods and high bed load transport, the river course frequently changed. A braiding river - floodplain system with large gravel banks, grey alder, willow wetlands, and wetland meadows characterized the valley.
  
 
==Measures selection==
 
==Measures selection==

Revision as of 12:14, 12 February 2014

Drava - Kleblach


Factsheet: Drava - Kleblach

General
Country AT
River Name Drava
Site Name Drava - Kleblach
River Characterisation
    River typology
    Location (Lat Lon) 46.75454, 13.309393
    Altitude mid-altitude: 200 - 800 m
    Catchment area large: > 1000 - 10000 km2
    Geology Siliceous
    National code/
    River type name
    Hydromorphological quality elements

    Biological quality elements
    Ecosystem Services
    EU Directives
    Pressures
    Measures
    Other
    Project size 1.9 km
    Approximate costs > 1 000 000 Euros
    Synergy Flood protection, ecology, recreation
    Status Realised
    Period of realization 2002 - 2003
    Evaluation Hydromorphological and ecological changes
    Implemented by Amt der Kärntner Landesregierung, Abteilung 18 - Wasserwirtschaft


    Key features of the case study

    As part of the LIFE Nature project “Restoration of the wetland and riparian area at the Upper Drau River” several measures were implemented at the site of Kleblach. Bank stabilization structures were removed and the river bed was widened. Lateral erosion increased the sediment input and initialized the development of gravel / sand bars and islands. Furthermore the river bed incision decreased. One of the former side arms was reconnected to the river for annual flooding, and a second side arm was widened to a width of 30 m, creating diverse instream structures and increasing aquatic habitat diversity.

    Site description

    The Austrian river Drava (in German “Drau”) is part of the Danube catchment. The source of the river is in the Italian municipality Toblach where it continues its flow 264 km along the border between the Central Alps and the Southern Alps and across the Austrian federal states Tyrol and Carinthia. In Osijek (Croatia), the river joins the Danube River after 707 km in total. The site of the restoration project is located near the village of Klebach in Carinthia. At this point the Drava has a discharge basin of roughly 2500 km². The average annual flow of the river near the site is 63m³/s. The river at the site was historically braided with gravel banks in the channel. Until approximately 140 years ago, the Upper Drava was a free flowing, meandering mountain river with numerous braiding stretches due to alluvial cones of the tributaries. In this dynamic river system with its annual floods and high bed load transport, the river course frequently changed. A braiding river - floodplain system with large gravel banks, grey alder, willow wetlands, and wetland meadows characterized the valley.

    Measures selection

    Success criteria

    Ecological response

    Hydromorphological response

    Monitoring before and after implementation of the project

    Socio-economic aspects

    Contact person within the organization

    Extra background information