==General description ==
 
==General description ==
 +
This measure is described as an alternative for the very similar measure to manage dams for sediment flow in the respective fact sheet [http://wiki.reformrivers.eu/index.php/Manage_dams_for_sediment_flow Manage dams for sediment flow].
  
==Applicability ==
 
==Expected effect of measure on (including literature citations): ==
 
*HYMO (general and specified per HYMO element)
 
*physico � chemical parameters
 
*Biota (general and specified per Biological quality elements)
 
==Temporal and spatial response  ==
 
 
==Pressures that can be addressed by this measure ==
 
==Pressures that can be addressed by this measure ==
 
<Forecasterlink type="getPressuresForMeasures" code="M14" />
 
<Forecasterlink type="getPressuresForMeasures" code="M14" />
==Cost-efficiency ==
 
 
==Case studies where this measure has been applied ==
 
==Case studies where this measure has been applied ==
Continuous Sediment transfer is successfully being applied e.g. at Olsberg Reservoir of operator RWE since 2011. An automated vessel provides year round sediment transfer, except during ice coverage. Over time the vessel strikes the complete reservoir ground to transfer incoming sediment which deposited on the reservoirs floor. The sucked sediment is pumped to the aligned hydro power plant where the sediment is dropped in front of the turbine inlet and transferred through the turbine to the downstream river. The turbine ensures a good mixing with the outflow. Turbine components are not affected at the given sediment ratio.<br />
 
 
A scaling instrument aboard the vessel allows for automatically adjusting a sediment transfer volume which suits to the actual plant/reservoir outflow and downstream compatibility. Transfer capacity at this application is up to 20 t/day, depending on the reservoirs outflow. The downstream river as well as the reservoir itself experienced a significant increase in ecological condition assessment within only weeks.<br />
 
 
[[File:V 101 Agger.jpg]]
 
Automated Sediment Transfer Vessel (photo courtesy of DB Sediments). <br /><br />
 
 
 
<Forecasterlink type="getProjectsForMeasures" code="M14" />
 
<Forecasterlink type="getProjectsForMeasures" code="M14" />
  
==Useful references ==
 
==Other relevant information ==
 
  
 
[[Category:Measures]][[Category:02. Sediment flow quantity improvement]]
 
[[Category:Measures]][[Category:02. Sediment flow quantity improvement]]

Latest revision as of 08:55, 25 June 2015

Improve continuity of sediment transport

Category 02. Sediment flow quantity improvement

General description

This measure is described as an alternative for the very similar measure to manage dams for sediment flow in the respective fact sheet Manage dams for sediment flow.

Pressures that can be addressed by this measure

Case studies where this measure has been applied